March 24th update
The build must be finished by June 20, 2011, in order for Theatre by the Bay to move in for Tech Week and pre-show rehearsals.
Crew continue to work on the ceiling truss.
Scaffolding is installed in the backstage area. Another wall would be installed dividing the Backstage stairway and the stage.
Badger Daylighting makes a non-invasive excavation backstage. Badger uses a water and vacuum system to perform an excavation without harming utility lines.
The Front of House roof was installed on March, 22, 2011.
Keep you Ears to the Tracks on the Progress of the Downtown Community Theatre
Page Index
1. Introduction
2. The Glory Days
3. The Demolition
4. The Build
5. The Build Continues
6. The Fourth Wall
7. St Patrick's Day Update
8. Spring Update
9. April Fools Update
10. April Fools Update Part II
11. The April 8 Update
12. The April 13th Update
13. Palm Sunday Update
14. Easter / End of April Update
15. Mother's Day Update
16. Lion King Update
17. Victoria Day Update
18. May 26, Update
19. Celebrate Barrie Update
20. The Pentecostal update
21. Canada Day Update
22. The Tempest Update
23. Post Surgery Update
24. Grand Opening Update
Exciting Links
Theatre By the Bay
Volunteer for Theatre By the Bay
Talk is Free Theatre
No comments:
Post a Comment