Wednesday, June 1, 2011

Barrie Downtown Community Theatre: Under the Knife Part XX

Celebrate Barrie Update


On June 4th, Come down to Centennial Beach and Celebrate Barrie with free entrainment for the whole family.



Crew members work inside the house to get it ready for that big day.



Crew members finish installing Pink Panther insulation panels.

May 31 - June 1, 2011





On May 30th, work crew started installing Durock Cement panels on the east exterior wall.







On May 31, 2011 Crew members finally finished installing the Durock Panels on the Stage Right Wall







This is some great progress on the Downtown Theatre.  This crew member starts to install a tile finish on a wall in the Front of House.





Crew members using a level and taking a measurement.


A crew member continues to install the decorative tile finish in the front of house.

June 1, 2011



On the Second of June, Crews continue to work and catch up due to the rainfall in May.  Pink Panther panels are being installed on the Backstage wall (Prospero's Cell).  Crew members work hard inside the house on scissor lifts



A crew member install a new door.



A crew member cuts a piece of Pink Panther Insulation.


The Crew member wedges the piece of insulation behind the beam on Prospero's Cell




A crew member continues working on the decorative tile in the Front of House

June 2, 2011







Crew members load and install the decorative panels into the elevator car



Crew members work hard getting the Pink Panther Panels installed on the Back of House (Prospero's Cell)



Crew members continue installing decorative tile in the Front of House


By the end of the day, The Pink Panther Panels are almost installed.  Crew members have to cut and wedge the last few panels along the beam.

June 3, 2011




A crew member is taking measurements before the first Durock Cememt Board is installed on the Backstage wall



Crew members replace the concrete on the curb on Bayfield Street.




A Crew member measuring off a Durock Panel.



Over the Lunch hour, one painter makes his final brushstroke on the Stage Right Fire Door.




Two Durock Cement Panels are now installed on Prospero's Cell


By the end of the day, Crews installed the roll-up door on Prospero's Cell.  More work will continue inside the house.




The first five decorative tiles are installed on the Stage Right wall.




These crew members worked over the supper hour getting the vestibule installed.

Read Pentecost Update for more great details on the Downtown Community Theatre

July, 6, 2011





Join us for the Shakespeare Symposium

Georgian College Theatre

1 Georgian Drive, Barrie, ON
Your 49.00 + HST ticket includes

Reception and artist bazaar 

Directors Talk

Matinee performance of The Tempest

And More



A Free Ad by Philip Lock, supporting Live Professional Theatre in Barrie, ON

Page Index




Easter  / End of April Update

Mother's Day Update 

The Lion King Update 

Victoria Day Update 

May 26, Update

The Pentecostal update

Canada Day Update

The Tempest Update 

Post Surgery Update

Grand Opening Update